Phoenix, ArizonaNationwide Delivery
KorFab component fabrication in Phoenix, Arizona

Preparing a Component Package for an Equipment Build

An equipment build needs many small parts from one drawing set. Organizing them into a reviewable package is what makes the whole batch quote in one pass.

Dan Caronna, Vice President

An equipment build does not arrive as one drawing. It arrives as a frame, a set of brackets, some covers, a guard and a handful of plates, spread across an assembly tree. The fabrication quotes that go wrong are usually the ones where those parts were sent as twenty separate conversations.

Organize by assembly, not alphabetically

Send the package the way the machine is built: top level assembly, then sub assemblies, then the individual parts. That structure is how the review checks that nothing is missing, and it is how the order is packed and identified at delivery.

A flat list of parts with no parent assembly is workable for a small job and unhelpful for a build with more than about twenty parts.

Number the parts once

Use the numbering already in your drawing set and keep it on every document: drawing, bill of materials, finish schedule, packing list. Where a part repeats across sub assemblies, say so rather than listing it twice under two numbers.

Group by process, then state quantities

The review is faster when the package shows which parts are cut only, which are formed, which are welded sub assemblies, and which need coating. That grouping also exposes the parts that are nearly identical, which is where a fabricator can point out that two brackets differing by one hole could be one part with a change.

Quantities per assembly, and the number of assemblies being built. A component count of forty brackets usually means twenty per machine and two machines, and the difference matters for how the run is set up.

Say what you supply

Bought in items, castings, bearings, motors, fasteners. A component package that includes purchased parts without saying so invites a quote for making something that was never going to be fabricated.

Material and finish consistency

Where a build uses one material and one finish across most parts, say it once at package level and note the exceptions. That single line removes the most repetitive part of any review, and it prevents a bracket arriving in the wrong coating.

What the review returns

A first package usually comes back with questions: a dimension that does not close, a hole pattern referenced to a face that does not exist, a finish that appears on the drawing but not the schedule. That is normal on a first build and it is cheaper than a part that arrives wrong.

Where this goes next

If the equipment repeats, repeat production metal components covers how the package continues across builds, and how to organize a multi part fabrication request covers a package that is not organized by assembly.